After the original Riverwalk was destroyed in the catastrophic floods of 2011, John Holland engaged Bendworx's expertise to help rebuild the iconic walkway.
The new Riverwalk design required it to be strong enough to withstand a 1 in 2000 year flood – depths of up to 9 metres and up to 18,000m3 of water per second.
Our Steel Pipe & Casing division was contracted to supply, manufacture, test, certify and deliver to site quality-assured multi-stage pile casings to the exacting engineering standards specified.
Working closely with project engineers and piling specialists over 18 months we responded to developing situations on the ground to continually exceed expectations.
We are proud to have been a key part of our home city’s healing, and look forward to Riverwalk being a key attraction for many decades to come.